The total lead time for a custom jacket order from Ginwenwear typically ranges from 6 to 12 weeks from sample approval to delivered goods, depending on order quantity, material availability, and shipping method.
Lead Time by Phase
| Phase | Duration |
|---|---|
| Sample Development | 7-10 working days |
| Sample Revision | 3-5 days per round |
| Bulk Material Procurement | 10-20 days |
| Bulk Production (50-500 pcs) | 15-25 working days |
| Bulk Production (500-2,000 pcs) | 25-35 working days |
| Final QC and Packing | 3-5 days |
| Sea Freight to US West Coast | 20-28 days |
| Sea Freight to US East Coast / Europe | 30-40 days |
| Air Freight | 5-8 days |
| Express Courier (DHL/FedEx/UPS) | 3-5 working days |
Timeline Scenarios
For a 300-piece bomber jacket order with sea freight to the US: approximately 11 weeks total. For an urgent 100-piece puffer order with air freight: approximately 6 weeks. For a 2,000-piece down jacket order with custom fabrics: approximately 15 weeks.
Factors That Extend Lead Times
Custom fabric dye lots add 5-7 days. Seasonal peak periods (February-April and August-October) add 5-10 working days. Multiple revision rounds add 3-5 days each. Third-party testing adds 7-14 days.
Planning tip: Build a 2-week buffer into your timeline to account for common delays and avoid expensive air freight.
Submit your inquiry for a customized timeline for your specific jacket order.
Are you looking for reliable manufacturers of down products?
We can quickly provide customers with market analysis, technical support and customized services.- *Name
- *Phone
- *Title
- *Content